Skip to content

Engineering Solution & Consultancy

Four checks at the basic-design gate

  • Engineering Solution & Consultancy
  • 1 min read

Before detail design opens on a GMP project, the basic-design gate should have four things on the table.

  1. Room data sheets and the pressure cascade frozen, with a grade, a target differential and a door swing for every room.
  2. The HVAC load calculation matching the equipment list, so the AHU sizes in the list are the ones the loads produce.
  3. A URS issued for each critical system: HVAC, purified water, the BMS or EMS.
  4. Every open item from the design review closed, or carried forward with a named owner and a due date.

When one of them is missing, detail design for the affected rooms should wait. The cascade is the expensive one to get wrong. A room that moves from Grade C to Grade B after the ducts are drawn usually needs more supply air, and that changes the supply duct, the number of terminal filters, the AHU selection and the pressure step to each neighbour. Every one of those drawings has already been checked once.

Schedule pressure pushes the other way, and a partial opening is often reasonable: areas whose rooms are frozen can start, while the rooms still moving wait for their data sheets.

Our project management consultancy runs stage gates from concept to PQ, with a live FMEA risk register and earned value reporting.

How our project management consultancy runs a GMP project

Industries

Related

More on this subject

Two envelopes for a cleanroom HVAC tender

Score the technical envelope of a cleanroom HVAC tender and sign it off before any price is opened. Issue the scoring sheet with the tender: mandatory items pass or fail, the rest weighted, for example 40% technical depth and 20% each for documentation, delivery and service. Score every listed deviation.

InsightRead