Hydrogen is flammable in air from about 4% by volume and weighs about a fourteenth as much as air, so it rises and stays up.
Electrolyser halls therefore get detectors and extraction at the roof, and the roof is where it goes wrong. Deep beams and purlins make pockets that a leak can fill while the ridge detector a few metres away reads nothing. The fix belongs on the structural drawings: a roof without pockets, or a vent and a detector in each pocket, near the flanges, valves and stack connections.
A common alarm scheme gives a first alarm at 10% of the lower flammable limit, 0.4% hydrogen, and a second stage at 20–25% LFL that boosts ventilation and isolates the supply. The zone drawing comes from an IEC 60079-10-1 study.
In a Li-ion battery room the design question is less where the sensor sits than what it switches. A failing cell usually vents electrolyte vapour before thermal runaway, which releases mainly hydrogen, CO and CO2 with some HF. Off-gas sensors at rack level can see that first venting, but they only help if the cause-and-effect matrix does something with it, typically stopping charge, isolating the rack and starting ventilation. NFPA 855 is the usual reference for ventilation and explosion control.
Our renewables scope covers BESS safety and green hydrogen facilities.
Which LFL percentages trigger the ventilation boost and the shutdown on your site?