One room numbering scheme from room data sheet to door sign

  • Engineering Solution & Consultancy
  • 1 min read

If a filling room is 2.14 on the drawings, FR-02 in the batch record and zone 7 in the EMS, each investigation starts with a lookup.

Nobody chose three schemes. Each team numbered the rooms when it first needed to: the architect by floor for the layout, the process team by function for the URS, the automation integrator in the order it built the tag database. Each is reasonable alone. Side by side in a deviation, with a pressure excursion on the EMS trend, an entry in the cleaning log and a door on the cascade drawing, they cost hours and invite the wrong room.

One code, fixed early, avoids that. The room data sheet is the natural place, because it is the first document that describes each room on its own terms. From there the same code goes into:

  1. the architectural, HVAC and pressure cascade drawings,
  2. instrument tags, for example PDT-2.14-01 for that room's pressure transmitter,
  3. SOPs, logbooks, cleaning records and batch records,
  4. the sign on the door.

Two rules keep it working. A room split during design gets new codes, and a retired code is never reused. After handover, a code change goes through change control like any other qualified record.

Room definition in our design work starts from 34 standard pharma Room Data Sheets.

Related

More on this subject

Three APS runs across all shifts, and the HVAC has to hold still

Annex 1 initial validation of an aseptic process needs at least 3 consecutive successful simulations covering all working shifts, then periodic runs twice a year per process, line and shift. The cleanroom must hold its qualified state throughout. Agree an HVAC freeze date with QA, and list in advance which jobs are like-for-like and which need an impact assessment.