Re-specify the F9 on your spares list

  • News
  • 1 min read

The spares list for a five-year-old AHU still says "F9 bag filter", and the store reorders it that way every quarter.

F9 is an EN 779 class. EN 779 was withdrawn and replaced by ISO 16890, which groups filters by how much particulate matter they remove: ePM1, ePM2.5, ePM10, plus ISO Coarse. To be classed ePM1, a filter must remove at least 50% of particles in the 0.3 to 1 µm range. There is no exact conversion from F-classes, so a supplier asked for "F9" today picks whatever ISO 16890 filter it considers equivalent, and the next supplier may pick a different one.

In a GMP plant that matters twice. The pre-filter decides how fast the terminal HEPA loads, and a HEPA change in a classified room comes with a leak test. And a filter that differs from the one in the qualified design is a change, whether or not anyone raised it.

The fix is dull and cheap:

  1. Re-specify each pre-filter position in the asset register by ISO 16890 group and efficiency, with its initial and final pressure drop.
  2. Keep HEPA and ULPA positions on EN 1822 as they are: H13 ≥ 99.95%, H14 ≥ 99.995% at MPPS.
  3. Put the same line on the purchase code, so the store can only buy what was qualified.

Spare-parts and asset registers are part of our maintenance service.

Related

More on this subject

Three APS runs across all shifts, and the HVAC has to hold still

Annex 1 initial validation of an aseptic process needs at least 3 consecutive successful simulations covering all working shifts, then periodic runs twice a year per process, line and shift. The cleanroom must hold its qualified state throughout. Agree an HVAC freeze date with QA, and list in advance which jobs are like-for-like and which need an impact assessment.