Steam or adiabatic humidification in a GMP AHU

  • Life Sciences
  • 1 min read

Plants in northern Viet Nam can need winter humidification, and a GMP design copied from a southern plant may have no humidifier at all.

When one is added, the choice is steam or adiabatic, and in a GMP AHU the deciding question is microbial before it is energy.

A steam humidifier injects water vapour. If the distribution and absorption distance are right, no liquid reaches the airstream, and the water has been boiled. Starting from water at about 20 °C, each kilogram of steam takes roughly 0.72 kWh: about 0.63 kWh to evaporate it at 100 °C and 0.09 kWh to bring it to the boil. The source matters: plant boiler steam can carry corrosion-inhibiting amines, which should not go into supply air for a clean area. Clean steam from a pure steam generator, or a local electric steam generator on treated water, avoids that.

The trouble with adiabatic units in a GMP AHU is the water. It has to be treated, kept moving and disinfected, because standing or recirculated water in an AHU grows organisms, and droplets that are not absorbed wet the filters downstream. The evaporation heat also comes out of the air itself, so in winter the supply air cools and needs more reheat.

For most GMP supply units we would take steam, fed from clean steam where the plant already has it. Adiabatic can earn its place in a non-GMP area with good water treatment and a maintenance plan that actually runs.

Talk to an engineer: contact@humiley.com · +84 28 7777 6668 (Viet Nam office)

Industries

Related

More on this subject

Four checks at the basic-design gate

Before detail design opens, a GMP project should have frozen room data sheets and pressure cascade, loads that match the equipment list, a URS for each critical system and owned open items. A cascade change after the ducts are drawn reaches the duct sizes, terminal filters, AHU selection and every neighbouring pressure step.

InsightRead