The filter change record: five things it has to show

  • News
  • 1 min read

A filter change record with a date, a filter class and one signature cannot show the room went back to the state it was qualified in.

The questions come later, from QA or an inspector, and the record has to answer them. Five things belong on it.

  1. Isolation. Which AHU or FFU was stopped, how the rooms it serves were protected, and that production knew. A permit number is enough if the permit carries the detail.
  2. Bagging. The loaded filter bagged inside the unit before it crosses clean space, and how it was disposed of. For potent or biological duty that means a bag-in/bag-out housing and its own procedure.
  3. Frame and gasket check. Clamps, knife edge or gasket, and the frame itself, looked at with the old filter out. A damaged gasket left under a new filter is a bypass.
  4. ΔP before and after. The final ΔP of the old filter confirms why it came out. The initial ΔP of the new one is the baseline its own change point is set from.
  5. The leak-test decision. A terminal HEPA replaced, or its seal disturbed, gets an installed leak test before the room goes back into use. A pre-filter change in the AHU usually does not, though room pressures and airflow deserve a check once the fan settles.

Filter changes, and the requalification tests that follow them, are part of Humiley's Maintenance Service.

More engineering notes on our news page

Related

More on this subject

Four maintenance KPIs for a GMP plant

A single PM compliance percentage hides the overdue task QA cares about. Track PM compliance by criticality, overdue critical tasks listed by name, repeat failures on the same asset, and mean time to restore the pressure cascade from the BMS trend. All four need a CMMS asset register with criticality assessed.

InsightRead