Room Data Sheets first: fix the room before the drawing

  • Life Sciences
  • 1 min read

Drawings are the wrong place to find out what a room needs.

A Room Data Sheet is one page per room, agreed by process, QA, engineering and maintenance before layout drawings start. It turns the URS into numbers a designer can size from. Our library of 34 standard pharma Room Data Sheets gives that first draft.

What an RDS fixes early:

Grade and classification, at rest and in operation.

Temperature and RH ranges, with the tolerance that actually matters to the product.

Pressure relative to each neighbouring room, and airflow direction at every door.

Occupancy, equipment heat and moisture loads, and whether the process releases dust or solvent.

Finishes, lighting level, utility outlets, door interlocks and environmental monitoring points.

Every one of those lines changes an airflow, a duct size or a piece of equipment. Change them after the HVAC schematics are issued and you redo the load calculation, the pressure balance and often the AHU selection.

A standard library doesn't replace the conversation with your process team. It shortens it, because people are correcting a draft instead of filling a blank page.

Talk to an engineer: contact@humiley.com · +84 28 7777 6668 (Viet Nam office)

Industries

Related

More on this subject

The first 90 days of a GMP maintenance takeover

Taking over HVAC maintenance in a running GMP plant starts with four outputs in the first 90 days: a walk-down of every asset behind a GMP parameter, a criticality ranking, the calibration status of every BMS and EMS input, and ownership of open HVAC deviations and CAPAs.

InsightRead