A tablet press with its own dust extraction takes air out of the compression room every time it runs.
If that airflow is missing from the room data sheet, the room balance is wrong from day one.
The symptom is a pressure to the corridor that shifts whenever extraction starts and stops, and a balancing contractor chasing it with dampers that cannot fix it.
The rooms either side of compression on an OSD line load their HVAC in other ways. In wet granulation the wet mass and the fluid bed dryer put moisture into the room, some formulations add solvent vapour, and dry milling afterwards makes dust, so humidity control and sometimes hazardous-area classification come up before anyone talks about air changes. A coating pan brings heat and a second air system with its own supply and exhaust, which the room HVAC has to be balanced against; solvent coating raises the hazardous-area question again.
None of these loads is visible on a layout drawing. They have to be written down room by room: the process step, the equipment list, every local extraction point with its airflow, equipment heat, moisture and solvent sources, whether product is exposed, and the containment level. Only then is the supply air sized.
Humiley keeps a library of 34 standard pharma room data sheets as the template for this.
Which local extraction flow has caught you out at balancing?