A common misreading: "risk-based requalification" means you can stretch the interval if nothing has gone wrong. It works the other way.
EU GMP Annex 1 (2022) sets maximum intervals: 6 months between requalifications for Grade A and B cleanrooms, 12 months for Grade C and D. A risk assessment can justify testing more often, or adding tests, where the process or the monitoring history calls for it. It is not a route to longer gaps in a sterile suite.
What a periodic requalification retests:
- Classification by particle count to ISO 14644-1.
- Filter integrity: installed HEPA leak test by aerosol scan.
- Airflow volume.
- Pressure differentials between adjacent rooms and grades.
- Air velocity: required for filling zones under unidirectional airflow, and set by the CCS risk assessment in Grades B, C and D. In rooms without unidirectional airflow, a recovery test replaces the velocity test.
The calendar is not the only trigger. A filter replacement, an AHU modification or a layout change goes through change control and may need partial requalification whatever the date is.
Our maintenance team plans requalification from the same asset register and criticality assessment as the rest of the maintenance program, so the test dates don't live in a separate spreadsheet.