The URS says tablets, capsules and an annual tonnage. The SKU list that sets the number of packaging lines is in a sales spreadsheet.
Output in kilograms sizes the granulation suite. The number of SKUs, their batch sizes and their packs size nearly everything downstream of compression, and the design team often sees that list after the layout is frozen.
Before the layout is drawn, check that the list covers five points.
- Changeovers per week on each packaging line. Many small batches mean more time in line clearance, and that decides how many lines and packaging rooms there are.
- Pallet positions by SKU, and how much part-pallet picking the warehouse does.
- The printed materials store. Each SKU brings its own carton, leaflet and label or foil, and all of it is held under secure, controlled access.
- Format parts. Every blister size and bottle size has change parts that need a clean, labelled store near the line.
- Which products run in campaigns on shared equipment and which are dedicated. That decides which rooms can share an air handling unit.
The list keeps changing after handover, so the URS should state the SKU count assumed and the growth allowed for. We write the URS in parallel with the design, which is when the question is cheapest to ask.
None of this needs final numbers. A low case and a high case per line is enough.