Monday: the site utilities engineer raises the chilled water supply temperature to save chiller energy.

Wednesday: the AHU coils can no longer hold the dew point in the Grade C suite. Friday: two teams find out that each thought it owned the design basis.

No one made a bad decision. The problem was that nobody had agreed where the decision sat.

Many owners have strong in-house engineering teams, and that is a good thing. They know the site, the maintenance culture and why decisions were made ten years ago. What makes the collaboration work is agreeing three things, in writing, early:

Who owns the design basis: a named person, who holds the document and its revision history.

Who decides and who is consulted on each shared parameter: chilled water temperatures, power allowances, room grades, the control platform. A RACI that everyone has actually read.

How changes move. A change to a shared parameter goes through the owner, with its effect on the other disciplines assessed before it is issued.

On most projects this fits in a two-page table agreed at the first project meeting.