The 10 seconds a generator cannot cover

  • News
  • 1 min read

A Type 10 generator has 10 seconds to pick up the load. A PLC, an EMS server or a network switch will not wait that long.

NFPA 110 classifies emergency power systems by how fast power comes back. Type 10 means within 10 seconds of the normal supply failing. For a diesel set that is quick work: detect the failure, crank, reach speed and voltage, close the transfer switch.

For motors and lighting, 10 seconds is fine. For controls it means a restart, and a restart can take minutes. An environmental monitoring system drops its connection and leaves a gap in the record at the moment the room pressures were disturbed. A BMS that reboots may come back in a default state rather than the one it was running in.

So the UPS and the genset do different jobs. The UPS bridges the 10 seconds the genset cannot cover, plus the time the controls need to see stable power again. Size it on the loads that must not blink: controllers, monitoring, network, the historian, and the EMS sensors if they are powered centrally. The fans stay on the generator.

Test it the way it will fail. A black-start test that pulls the incomer shows what restarts and what keeps running, which is rarely what the single-line diagram suggests.

Talk to an engineer: contact@humiley.com · +84 28 7777 6668 (Viet Nam office)

Topics

Related

More on this subject

The first 90 days of a GMP maintenance takeover

Taking over HVAC maintenance in a running GMP plant starts with four outputs in the first 90 days: a walk-down of every asset behind a GMP parameter, a criticality ranking, the calibration status of every BMS and EMS input, and ownership of open HVAC deviations and CAPAs.

InsightRead

The room data sheet changes jobs at qualification

A room data sheet begins as a design input that changes weekly and ends as the qualified record behind OQ, PQ and monitoring limits. Each role needs different revision control. Agree the freeze point before DQ, so design and QA are never editing different versions of the same room.

InsightRead

The vendor drawing review before fabrication

Substitutions reach site through vendor drawings approved in a hurry. Before releasing fabrication, check the duty point at design conditions, materials in the air path, clearances against the BIM model, sensors against the BMS I/O list, and the certificates and FAT procedure that must come with the unit.

InsightRead