"High-efficiency filtration" in a tender can come back priced as three different filters.
Two offer H13. The third offers H14 in a housing with no scan access, so the installed leak test cannot be done without taking the ceiling apart. All three comply with the sentence as written, because it asked for nothing a test could fail.
The line that closes the gap names the class, the standard and the test: "H14 to EN 1822, installed filter leak test to ISO 14644-3". The first half fixes the filter itself, by a laboratory test at the most penetrating particle size (MPPS), where H14 means at least 99.995% efficiency. The second half fixes the filter in the room: an aerosol challenge upstream and a probe scan across the filter face and its seal.
That second half has a consequence people miss. The housing now has to allow the scan, with an upstream aerosol injection point, an upstream sampling port and room for the probe. So the housing gets its own line in the specification. The access details can be left to the vendor, as long as the scan is possible once the ceiling is closed.
Before issue, we also check each clause against what vendors actually build. A requirement nobody on the market can meet turns into a delay of its own.
Topics