Fire dampers fail closed. That is their job, and it is also how a supply branch goes dead while the AHU reports healthy.
A curtain damper is held open by a fusible link. Links corrode, fatigue under vibration or get knocked during other work above the ceiling, and the blades drop with no fire anywhere. The AHU keeps running. Fan status, supply temperature and filter pressure drop all look normal on the BMS.
Downstream, the rooms on that branch lose their supply. Where rooms have pressure monitoring, an alarm arrives and people start at the AHU and the filters. Where they do not, the first sign is a complaint about temperature a day later. Either way the search ends above a ceiling, at a damper with no access door that nobody tagged.
What the design around it left out is a way to reach it and a way to see it: an access door on the side from which the link and blades can be reset, and a closed-position switch wired to the BMS.
Then test it on the interval the fire code sets, and record the result.