Vendor drawings tend to arrive the week the factory wants to start cutting metal. That is the week substitutions get through.
Nobody plans a substitution. A coil loses a row to fit a frame, a drain pan material changes because stock ran out, a sensor range is copied from the last job. Each is found on site, where it costs most to fix.
We review every vendor drawing against the design basis before fabrication is released. What we check, in order:
- Performance at the duty point, not the catalogue: airflow at the system's external static pressure, and coil capacity at the wet-season design entering conditions.
- Materials and finishes in the air path: inner casing skin, drain pan material and fall, gaskets.
- Dimensions against the BIM model: service clearance, filter withdrawal space, the side each duct and pipe connects on.
- Instruments and controls: sensor type and range, and signals that match the BMS I/O list.
- The documents that must come with the unit: material certificates, weld and passivation records where relevant, and the FAT procedure.
Long-lead items are released only against approved documents. It can feel slow in the week it happens. It is much faster than a rejected unit at site acceptance.
Procurement into construction is one of the four handovers we manage on every project, and this review is most of it.