Vendor drawings tend to arrive the week the factory wants to start cutting metal. That is the week substitutions get through.

Nobody plans a substitution. A coil loses a row to fit a frame, a drain pan material changes because stock ran out, a sensor range is copied from the last job. Each is found on site, where it costs most to fix.

We review every vendor drawing against the design basis before fabrication is released. What we check, in order:

  1. Performance at the duty point, not the catalogue: airflow at the system's external static pressure, and coil capacity at the wet-season design entering conditions.
  2. Materials and finishes in the air path: inner casing skin, drain pan material and fall, gaskets.
  3. Dimensions against the BIM model: service clearance, filter withdrawal space, the side each duct and pipe connects on.
  4. Instruments and controls: sensor type and range, and signals that match the BMS I/O list.
  5. The documents that must come with the unit: material certificates, weld and passivation records where relevant, and the FAT procedure.

Long-lead items are released only against approved documents. It can feel slow in the week it happens. It is much faster than a rejected unit at site acceptance.

Procurement into construction is one of the four handovers we manage on every project, and this review is most of it.

See how we work on our services page.

Related

More on this subject

What to check on every BMS graphic

Operators run the plant from BMS graphics, so errors there become operating errors. Check each screen for five things: every value has a unit and a tag, the setpoint sits beside the actual value, alarm colours follow one convention, stale values look different from live ones, and room names match the room codes.

InsightRead

Fixed-speed FFUs slow down as their HEPA loads

A fixed-speed fan filter unit loses airflow as its HEPA filter loads. Set at 0.45 m/s, it has 20% to lose before the 0.36 m/s bottom of the Annex 1 guidance range. Constant-airflow EC units hold velocity if they are selected at the final pressure drop, and their speed trend doubles as a filter-loading record.

InsightRead

Handover formats maintenance can use

Split the handover by use. As-built CAD or BIM, the asset register, PLC and BMS source and the control narrative come in native, editable form. Signed protocols and certificates come as searchable PDF. One index by system and tag joins them, and the formats go into the contract before the first document.

InsightRead