A 1% pressure transmitter ranged 0–1,000 Pa can be wrong by ±10 Pa. On a 10 Pa cascade step, that is the whole step.
Most transmitter datasheets quote accuracy as a percentage of full scale, so the error in pascals follows the span. A transmitter specified 0–50 Pa at 1% of full scale is within ±0.5 Pa, small enough to see a door seal going. Re-ranging a 0–1,000 Pa unit down to 50 Pa rarely gets you there: the base sensor error stays, and many datasheets add a turndown penalty on top.
Wide ranges get installed for understandable reasons. One part number for the whole site. A spare that fits anywhere. The cost shows up later: the BMS reads 12 Pa, the real value could be anywhere from 2 to 22, and the alarm at 8 Pa is set inside the noise.
Adjacent grades are typically 10–15 Pa apart, so a few checks are worth doing before the next requalification:
- Read the datasheet line. Some devices quote % of reading, some % of full scale, some add a separate zero drift, temperature effect and turndown factor.
- Specify room differential transmitters for the job, 0–50 Pa or ±50 Pa for most cascades.
- Calibrate near the working value, not only at zero and full scale.
- Set alarm limits with the total instrument error written next to them.