A technology transfer is finished when its report says so, measured against acceptance criteria written into the protocol beforehand.
WHO's guideline on technology transfer (TRS 1044, Annex 4) puts it that way round. The acceptance criteria for a successful transfer should be documented in the protocol a priori. A technology transfer report should then be prepared, should include an assessment of the data and a conclusion, and should be authorised by the appropriate responsible person or persons.
Before signing one, look for these entries:
- A result against each acceptance criterion in the protocol. "All batches complied" is not a result.
- The critical parameters as obtained at the sending unit and at the receiving unit, side by side.
- Every deviation and change from the plan, each with its assessment. The guideline says these should be assessed and evaluated before close-out.
- A conclusion that states whether or not the transfer has been completed.
- The authorising signatures. In practice that means the sending unit, the receiving unit and QA, and an owner and a date against any open action.
Some work runs past the signature. The Annex's project review should also make sure, as appropriate, that stability studies are started and continued, post-marketing commitments are monitored and new material suppliers are brought into the quality system.