Cut the SKU list before the transfer starts

  • Engineering Solution & Consultancy
  • 1 min read

Each SKU left on a transfer list has to be covered by validation and stability work, so cut the list before anything is planned against it.

Most lists are shorter than they look. To find out by how much:

  1. List every SKU with its strength, pack, market, annual volume and the date it was last made. The last column is usually the surprise.
  2. Group them by formulation, process and pack line. Say sixty SKUs come down to twelve bulk products on three packaging lines.
  3. Decide which SKUs to retire or merge. This is a commercial and regulatory decision for each market, made before anyone orders format parts.
  4. Choose the extremes within each group for validation and stability, where bracketing is allowed.
  5. Order the transfer by value and risk: a high-volume, simple product first, to prove the route.

For validation, EU GMP Annex 15 (2015) says that for products transferred between sites the number of validation batches could be reduced by a bracketing approach, with existing product knowledge available, and that different strengths, batch sizes and pack sizes may also use bracketing if justified. For stability, ICH Q1D (2002) says bracketing generally should not be applied where strengths use different excipients.

Talk to an engineer: contact@humiley.com · +84 28 7777 6668 (Viet Nam office)

Related

More on this subject

Engineering's part of the product quality review

The 2013 text of EU GMP Chapter 1 lists the qualification status of relevant equipment and utilities among the items a product quality review should include. Engineering can make that line believable with four more inputs: changes in the period, excursions and trends, calibration and maintenance failures with product impact, and the status of engineering CAPAs.

InsightRead