Some owners come to us with a finished design and one sentence: the design exists, deliver it on a date and a budget.
That is a project management brief. The EPCM team runs the stage gates from concept to PQ, FAT, SAT and qualification included. The design stays with its designer of record, and that boundary should be written down before anyone signs. When a site condition or a vendor substitution touches the design, the question goes through change control and the designer answers it. A change made on site without that has nobody to defend it at qualification.
The awkward case is a design with gaps. The first stage gate is the place to list them, and a list that people actually use has five columns:
- The document or drawing.
- What is missing: a room with no pressure setpoint, an AHU with no datasheet, a clean-utility line drawn with no slope.
- The activity it blocks, such as the AHU order or an IQ protocol.
- Who closes it, usually the designer.
- The date it is needed by, read off the schedule of the activity it blocks.
Without the fifth column the list has no deadline. A gap with no date has no reason to close before OQ, and at OQ it usually comes back as a deviation and a retest.