When the design exists: what EPCM takes on

  • Engineering Solution & Consultancy
  • 1 min read

Some owners come to us with a finished design and one sentence: the design exists, deliver it on a date and a budget.

That is a project management brief. The EPCM team runs the stage gates from concept to PQ, FAT, SAT and qualification included. The design stays with its designer of record, and that boundary should be written down before anyone signs. When a site condition or a vendor substitution touches the design, the question goes through change control and the designer answers it. A change made on site without that has nobody to defend it at qualification.

The awkward case is a design with gaps. The first stage gate is the place to list them, and a list that people actually use has five columns:

  1. The document or drawing.
  2. What is missing: a room with no pressure setpoint, an AHU with no datasheet, a clean-utility line drawn with no slope.
  3. The activity it blocks, such as the AHU order or an IQ protocol.
  4. Who closes it, usually the designer.
  5. The date it is needed by, read off the schedule of the activity it blocks.

Without the fifth column the list has no deadline. A gap with no date has no reason to close before OQ, and at OQ it usually comes back as a deviation and a retest.

Related

More on this subject

Manufacturing & Distribution

Two envelopes for a cleanroom HVAC tender

Score the technical envelope of a cleanroom HVAC tender and sign it off before any price is opened. Issue the scoring sheet with the tender: mandatory items pass or fail, the rest weighted, for example 40% technical depth and 20% each for documentation, delivery and service. Score every listed deviation.

InsightRead

A retention that pays for the turnover file

Most of a cleanroom HVAC contract is paid before the turnover documents exist. Split the retention into two parts, released on acceptance of the turnover package and of the documents, and size the documentation part on what it would cost the owner to finish as-builts, calibrations and retests without the contractor.

InsightRead