An AHU that passed OQ in March in Ho Chi Minh City has not yet met the weather it was sized for.
In the dry season, outdoor air is hot but comparatively dry. A fresh-air coil reaches its leaving dew point with capacity to spare, balancing and OQ pass, and the humidity trend is flat.
Then the rains come. The hardest hour for a GMP AHU becomes a 29 °C afternoon with the outdoor dew point in the mid-20s. To hold 21 °C and 45% RH, air has to leave the coil at a dew point of about 8.5 °C or a little below, and reheat then brings it back up to supply temperature. That overcool-and-reheat is the normal way to reach the dew point. A coil selected on peak dry-bulb runs out of latent capacity exactly then: it can no longer reach that dew point, and room RH climbs.
Nothing in the dry-season record was wrong. It simply could not see the latent case.
Three things close that gap:
- Size the fresh-air coil on the dehumidification condition (peak dew point with its coincident dry-bulb) and write that condition on the AHU schedule.
- If OQ falls in the dry season, keep room humidity monitoring running through the first wet season and review it as part of PQ.
- Log outdoor dew point on the BMS beside room RH, so a wet-season drift can be read against the weather that caused it.