On multi-contractor sites the decisions between scopes go unowned first: envelope penetrations, punch-list closure, construction cleanliness, interface as-builts and turnover sign-off. A RACI works when it names those decisions, with one accountable person each, and is reviewed whenever a scope changes.
In an FMEA risk register, severity 10, occurrence 2 and detection 3 score an RPN of 60, below a nuisance risk at 100. Add a rule that any severity 9 or 10 comes to the weekly review whatever its RPN, and re-rate every risk after its mitigation.
Two independent long-lead paths, each 80% likely on time, give a 64% chance that both arrive for qualification. A qualitative FMEA register manages risks one at a time; a Monte Carlo schedule analysis adds them up and gives P50 and P80 dates. It earns its cost where paths converge on a fixed date.
Most of a cleanroom HVAC contract is paid before the turnover documents exist. Split the retention into two parts, released on acceptance of the turnover package and of the documents, and size the documentation part on what it would cost the owner to finish as-builts, calibrations and retests without the contractor.
EPC moves cost and schedule risk to one contractor at a fixed price; compliance risk stays with the owner under any contract form. If the tender never named who writes and executes the DQ, IQ, OQ and PQ protocols, the lump sum did not include them. Owners who cannot define that yet are often better served by EPCM.
Designer, supplier, contractor and maintenance team each hold part of a facility's design intent, and assumptions get lost at every boundary. Humiley works as four divisions on one design basis, so the drawing, the factory acceptance test and the maintenance plan all trace back to the same requirements.