Where RACI breaks first on a multi-contractor site

  • Project Management Consultancy
  • 1 min read

On a site with five contractors, the first thing to go missing is an owner for the decisions between two scopes.

Everyone owns their own package. The trouble lives at the joins. These are the ones we see drift most often:

  1. Penetrations through the cleanroom envelope. The duct is HVAC's, the ceiling panel is the cleanroom contractor's, the seal between them is often nobody's until the pressure test fails.
  2. Punch-list closure. Who confirms an item is closed: the contractor who fixed it, the supervisor who raised it, or the owner?
  3. Construction cleanliness. When the AHUs start, who decides the rooms are clean enough to run air through new filters?
  4. As-built drawings at interfaces. Each trade updates its own layer; the clash at the boundary goes undrawn.
  5. System turnover. Who signs that a package is complete and ready for qualification?

A RACI helps only if it names these decisions explicitly, not just the packages. Each line gets one person accountable, not a company, and the RACI is reviewed when a contractor's scope changes. The test of a good one is simple: pick a decision from the list and see how long it takes the site team to name the accountable person.

Our EPCM work runs with a RACI, a stage-gate plan and an audit-ready handover, and the interface lines are the ones we write first.

Related

More on this subject

Two envelopes for a cleanroom HVAC tender

Score the technical envelope of a cleanroom HVAC tender and sign it off before any price is opened. Issue the scoring sheet with the tender: mandatory items pass or fail, the rest weighted, for example 40% technical depth and 20% each for documentation, delivery and service. Score every listed deviation.

InsightRead

Annex 1's scope reaches non-sterile plants

The scope of EU GMP Annex 1 (2022) says some of its principles, including the contamination control strategy, may be used for certain non-sterile products such as liquids, creams and ointments. A semi-solids plant that writes a CCS tying room grades, flows, water and monitoring to product risk has an answer for the inspector.

InsightRead