On a site with five contractors, the first thing to go missing is an owner for the decisions between two scopes.
Everyone owns their own package. The trouble lives at the joins. These are the ones we see drift most often:
- Penetrations through the cleanroom envelope. The duct is HVAC's, the ceiling panel is the cleanroom contractor's, the seal between them is often nobody's until the pressure test fails.
- Punch-list closure. Who confirms an item is closed: the contractor who fixed it, the supervisor who raised it, or the owner?
- Construction cleanliness. When the AHUs start, who decides the rooms are clean enough to run air through new filters?
- As-built drawings at interfaces. Each trade updates its own layer; the clash at the boundary goes undrawn.
- System turnover. Who signs that a package is complete and ready for qualification?
A RACI helps only if it names these decisions explicitly, not just the packages. Each line gets one person accountable, not a company, and the RACI is reviewed when a contractor's scope changes. The test of a good one is simple: pick a decision from the list and see how long it takes the site team to name the accountable person.