When RPN hides a severity 10 risk

  • Project Management Consultancy
  • 1 min read

Severity 10, occurrence 2, detection 3 gives an RPN of 60. A nuisance risk rated 4, 5 and 5 scores 100.

Sort a project risk register by RPN alone and the risk that could stop a qualification sits below the one that costs a week. A register needs a second rule next to its threshold: any risk with severity 9 or 10 comes to the weekly review whatever its RPN.

Our EPCM teams run the register as a live FMEA, reviewed every week. Each risk carries severity, occurrence and detection ratings, an owner, a mitigation with a date, and a status. Re-rating after the mitigation is the step that gets skipped. If a new inspection hold point was added and the detection score has not moved, either the hold point detects nothing or nobody re-scored it.

For the owner-side project manager, the high-severity lines tend to be long-lead equipment, vendor drawing approvals, utility connections, permits and qualification readiness. The same register feeds the monthly report, next to schedule, cost and earned value, so a risk that stays at severity 10 for three months is visible to the steering committee as well as the site team.

Project Management Consultancy (EPCM)

Related

More on this subject

Contractor self-commissioning is cheaper but lacks distance; an independent commissioning agent costs a fee and works for the owner. QA needs independence only on the results it will rely on: pressure cascade, air change rates, HEPA leak tests, alarms and interlocks. The rest can be self-commissioned and spot-checked.

InsightRead

A month-end note from Tony Nguyen, CEO

After more than twenty years with automation vendors and running an EU-GMP EPC contractor, Tony Nguyen saw problems start at the handovers between companies rather than inside any one scope. This note explains why Humiley is organized as one accountable team across design, project management, equipment and maintenance.

InsightRead