Severity 10, occurrence 2, detection 3 gives an RPN of 60. A nuisance risk rated 4, 5 and 5 scores 100.
Sort a project risk register by RPN alone and the risk that could stop a qualification sits below the one that costs a week. A register needs a second rule next to its threshold: any risk with severity 9 or 10 comes to the weekly review whatever its RPN.
Our EPCM teams run the register as a live FMEA, reviewed every week. Each risk carries severity, occurrence and detection ratings, an owner, a mitigation with a date, and a status. Re-rating after the mitigation is the step that gets skipped. If a new inspection hold point was added and the detection score has not moved, either the hold point detects nothing or nobody re-scored it.
For the owner-side project manager, the high-severity lines tend to be long-lead equipment, vendor drawing approvals, utility connections, permits and qualification readiness. The same register feeds the monthly report, next to schedule, cost and earned value, so a risk that stays at severity 10 for three months is visible to the steering committee as well as the site team.