If the EPC specification never defined the qualification deliverables, the lump sum never included them.
The owner still owes them to the inspector, and that is the part of the EPC or EPCM choice a first GMP plant tends to miss. Cost and schedule risk can be moved by contract. Compliance risk cannot: the GMP license, the URS, the qualification reports and the CCS stay the owner's documents whoever designs and builds the plant.
It changes how a lump-sum EPC tender should be written. One contractor designs, buys and builds for a fixed price and date, and settles every detail the specification leaves open, usually at the cheapest option that meets the words. Anything added after award is a variation, priced by the only design team on the job. So the tender has to name who writes and who executes the DQ, IQ, OQ and PQ protocols, and which FAT and SAT records and equipment files come with each package.
An owner who cannot write that list yet is usually better served by EPCM for now. The owner contracts the packages directly, a management consultant runs design, procurement and supervision on the owner's side, and cost risk stays with the owner in exchange for seeing every package price and design decision.
Humiley's Project Management Consultancy runs as EPCM, with stage gates from concept to PQ, earned value and a weekly FMEA risk review.
On your last tender, who was named to write the IQ and OQ protocols?
Industries