A lead-acid UPS battery that delivers 80% of its rated capacity in a discharge test has reached the end of its service life.
A string at 80% still carries the load today, so replacing it looks like waste. The figure comes from the IEEE recommended practices for stationary lead-acid batteries, IEEE 1188 for valve-regulated cells and IEEE 450 for vented ones. Both recommend replacement when a capacity test shows less than 80% of the manufacturer's rating. The reason is the shape of the ageing curve. Capacity fades slowly for years and then falls quickly, and at 80% the rate of loss is already increasing. A string that passes at 80% this year can be well below it at the next test.
End of life is therefore the sizing case. If the process needs 15 minutes, a battery that gives 15 minutes when new will not give them at 80%. Sizing practice (IEEE 485) applies an ageing factor of 1.25, which is 1 divided by 0.8.
A hot battery room brings that end forward. Design life is quoted at 20 or 25 °C, and a common rule of thumb for valve-regulated cells halves it for every 8 to 10 °C above that. A battery room that sits at 35 °C is using up its batteries about twice as fast.
At handover, ask for the capacity test result as a percentage of rating, with the date and the room temperature.