A leaky AHU casing lets the pressure cascade drift

  • News
  • 1 min read

0.15 liters per second per square meter at −400 Pa. That is the most an EN 1886 class L1 casing may leak.

L2 allows roughly three times as much. It sounds small. The problem is not the number on day one. It is how leakage behaves as the plant ages.

Room pressures in a cascade come from the offset between supply and return (or exhaust) airflow in each room. Commissioning sets those offsets with clean filters. Then the filters load, the fan speeds up to hold its flow, internal casing pressure rises and leakage rises with it. If the airflow measurement sits at the fan, the controller sees design flow while the rooms receive less. Offsets shrink, pressure controllers start hunting, and the cascade balanced in week one is not the cascade you have in month six.

The side of the fan matters too. Under negative pressure, a leaky casing pulls unfiltered plant-room air in past the pre-filters. Under positive pressure, it pushes conditioned, dehumidified air out into the plant room.

What to specify and check:

  1. Casing leakage class L1 for GMP duty, tested at negative and positive pressure.
  2. Filter bypass class F9, so leakage doesn't hide around the filter frames.
  3. A witnessed casing leakage test at FAT, with the result in the equipment file.

AeroSano hygienic AHUs are engineered from the project's airflow schedule and FAT-tested before they ship.

What leakage class did your last AHU submittal actually state?