AHU drain pans: slope, trap and inspection

  • News
  • 1 min read

The drain pans we open in older AHUs often hold water in one corner, downstream of the pre-filters and upstream of the final filters.

ASHRAE Standard 62.1 is specific about drainage. It asks for a drain pan sloped at least 10 mm per metre toward the outlet, with the outlet at the lowest point, so the pan drains completely instead of holding a film of water.

On inspections we keep finding the same faults:

  • a pan laid flat, or sagging, so water pools in one corner
  • a drain outlet set a few millimetres above the pan floor
  • no access door near the coil, so nobody has looked inside in years
  • a trap that has dried out, so the fan pulls air up the drain and holds the condensate back in the pan

The first three are design and FAT items, and they are cheap to catch before the unit is insulated and closed up. Put a level on the pan at the factory, measure the outlet against the pan floor, and open the access door to check you can actually see the pan.

The dry trap is the one that comes back after handover. Prime it after every long shutdown, and put a pan inspection on the maintenance task list with a photo in the record. If a bioburden result ever sends QA looking upstream, that photo series is the first thing they will ask for.

Talk to an engineer: contact@humiley.com · +84 28 7777 6668 (Viet Nam office)

Related

More on this subject

Manufacturing & Distribution

AHU vibration isolation, link by link

A spring isolator with its transport bolt still fitted transmits everything. Remove transport locks, select isolators for the lowest drive speed, keep flexible connections slack, remove rigid bridges such as conduit or drain lines, use inertia bases where needed, and file the balance report and a vibration baseline.

InsightRead