Coil face velocity and moisture carry-over

  • News
  • 1 min read

Above about 2.5 m/s face velocity, a wet cooling coil starts throwing water off its fins and into whatever comes next.

ASHRAE's coil guidance puts the usual limit for moisture carry-over from a dehumidifying coil at about 2.5 m/s (500 fpm). Above it, droplets leave the fin pack faster than the drain pan can catch them. They land on the next section: wet pre-filters, a wet casing floor, standing water where no drain was planned. In a pharma AHU that is a microbial problem before it is a performance one.

The pressure to go faster comes from the plant room. A smaller coil face means a smaller unit and a cheaper casing. For an AHU moving 5 m³/s, 2.5 m/s needs a 2 m² coil face. Squeeze it to 3 m/s and the face drops to about 1.67 m², so the unit gets shorter and narrower.

The saving comes back as cost elsewhere. An eliminator is needed downstream, adding pressure drop. The coil's own air-side pressure drop rises, roughly with the square of velocity. And the fan pays for both every hour it runs.

For hygienic AHUs we prefer to hold the coil at or below the carry-over limit and accept the larger section, rather than design in an eliminator with a wet zone behind it. On a tight plant room that is a genuine trade-off, and sometimes the plant room wins.

What face velocity does your standard AHU specification allow?

Related

More on this subject

Set a device assembly room's class from the product's risk

ISO 13485 §6.4.2 asks for documented contamination control without naming a cleanroom class. Setting the class from sterilisation method, patient contact and bioburden sensitivity often lands device assembly at ISO 8, with ISO 7 only where needed, less air than Grade C, a smaller AHU and a reason an auditor can read.