On a witnessed AHU factory acceptance test, the result sheet that both engineers sign carries four results.
Casing leakage comes first. A casing specified to EN 1886 class L2 may leak no more than 0.44 l/s per m² of casing surface at −400 Pa, and the rig on the test bay reads it directly. Fan airflow is then measured at the design external static pressure, and filter bypass is checked on the HEPA or final stage. Last comes the control panel, checked point by point against the approved drawing revision, with interlocks forced on the bench.
The signed sheet goes into the equipment file beside the material certificates and the weld and passivation records. When IQ starts on site, the record of who tested what, and against which revision, is already there.
Partnership is one of the five values Humiley works to. On the equipment side it has a concrete form: the client's engineer at the test bay, reading the same gauge as ours. The units we supply are built by qualified manufacturing partners under our engineering control, and every one is FAT-tested and witnessed.
For a witness visit to be worth the trip, two things need fixing in advance: a test date both sides can keep, and a specification frozen early enough to test against. If the spec is still changing in FAT week, the witness has no settled revision to check the unit against.
Which line on the FAT sheet do you always want to measure yourself?