On one AHU graphic the supply air temperature reads 14.2. It has no unit and no tag, and it has not changed since Tuesday.
Operators run the plant from these screens, so an error on a graphic turns into an operating error. It rarely gets reported, because nobody raises a deviation against a picture.
Graphics are usually reviewed once, at the SAT, by people checking that each point is mapped. A second review, by an operator who will run the plant from that screen, looks for other things:
- Every value shows its unit and its tag. A bare 14.2 could be degrees or a valve position, and without the tag it cannot be traced to an instrument and its calibration record.
- The setpoint is displayed beside the actual value.
- Alarm colours follow one convention on every screen. If red is "running" on the chiller page and "alarm" on the AHU page, people stop trusting red.
- A stale or failed value looks different from a live one. The 14.2 that has not moved since Tuesday is a dead link.
- Room names match the room codes on the drawings and in the batch record.
ANSI/ISA-101.01, the HMI standard for process automation, calls the document that fixes these conventions an HMI style guide. Have it written before the first screen is drawn. On a BMS job the guide is often the integrator's default library, so ask to see it at design stage, while a colour is still cheap to change.