A spring isolator with its transport bolt still fitted is a steel bracket, and fan vibration goes straight into the casing and slab.
Isolation in an air handling unit is a chain: fan and motor on springs, flexible connections, sometimes an inertia base. One rigid link and the rest does little. Most checks happen at installation and commissioning.
- Transport locks and shipping bolts removed, and every spring at its design deflection. A fan assembly that leans has unevenly loaded springs.
- Isolator deflection chosen for the lowest speed the drive will run, not only the rated speed. An isolator that suits full speed can resonate when a variable-speed fan turns down at night.
- The flexible connection (outlet on a housed fan, inlet cone to bulkhead on a plug fan) slack, never stretched tight, and made of a material that keeps the casing's leakage class and can be cleaned.
- Nothing else bridging the springs: rigid conduit, a drain line or a pressure tube pulled tight between the fan frame and the casing.
- An inertia base with its own isolators under large plug fans, or where a unit sits on a light roof structure.
- The impeller balance report in the FAT file, and vibration readings at commissioning kept as the baseline for trending.
AeroSano units are FAT-tested and witnessed, and the FAT report goes into the equipment file.