Year five: where the filter change limit comes from

  • Manufacturing & Distribution
  • 1 min read

Five years after handover, a technician changes the final filters on a supply AHU. The change point was set at design stage.

Follow that one number. In the design basis, the fan was selected to deliver the room's design airflow with the filters at their final, dirty pressure drop, not the clean one. That figure sits in the fan duty on the AHU drawing.

At FAT, the unit is run against the same duty. If the fan cannot reach design airflow at the dirty-filter allowance, it shows up in the factory, where the fix is a motor or a fan change on a bench.

At handover, the maintenance task for that AHU should quote the same figure as its filter change limit, with a reference to the fan duty it came from.

Trouble usually starts with a sensible-sounding request to stretch filter life by raising the limit. The fan then runs out of pressure before the filters are changed. Airflow falls, and the room's pressure differential drifts down while staying inside its alarm band, so the alarm list stays quiet and only the trend shows the margin shrinking.

With the fan duty cited on the task sheet, whoever proposes a new limit has to open the AHU drawing and look at the fan curve first.

At Humiley the design basis behind the drawing is also the one the FAT and the maintenance task list are written against.