O&M manuals tend to be accepted by weight: four binders delivered, signed for and shelved.

The real test comes later, when a technician opens one at night to find the setting of a differential pressure switch and finds a catalogue that covers the whole product range.

Before signing, open the manual at one system you know well and read it against the plant:

  1. It describes the equipment as built. Each unit appears with its tag, model and serial number, the as-built drawings are referenced, and options that were not supplied are struck out.
  2. Settings are listed by tag: setpoints, alarm limits, time delays and drive parameters, as left after commissioning.
  3. Each maintenance task has an interval and a method. "Inspect regularly" is neither.
  4. Spare parts carry the manufacturer's part number and the quantity per unit, with wearing parts marked.
  5. Fault-finding starts from the symptom the operator sees, and the supplier contact is a service line that answers.

Item 2 is the one a catalogue can never contain, and the one maintenance needs first. For the equipment we supply, the equipment file is compiled during production, O&M and spares included, so IQ starts from a complete record.

If the sample system fails, the rest of the manual probably does too, and it is cheaper to send it back before the final payment than to rebuild it from nameplates afterwards.