Every H14 filter is leak-tested at the factory and ships with its own test report. The next test it gets is in the ceiling.
Between those two tests come the truck, the store, the corridor and a ladder, and the media is a pleated glass-fibre paper that a fingertip goes straight through. Most of the damage happens in the last two metres: a thumb in the pleats, a gasket rolled on one side, a frame pulled down unevenly.
The sequence that avoids it:
- Clean the room and the housings, then run the system on its pre-filters, so the new HEPAs do not load up with construction dust.
- Unpack each filter at its point of use and carry it by the frame. Inspect both faces of the media and the whole gasket under a torch.
- Check the label against the position schedule: size, class, rated airflow, serial number.
- Seat the filter and tighten the clamps evenly, to the compression the manufacturer gives.
- Leak-scan the installed filter across the face and around the perimeter (the installed filter system leakage test of ISO 14644-3), and record the serial number against the ceiling position.
The in-place scan covers the seal and the frame as well as the media, which the factory test cannot do.
Reseating normally cures a leak at the gasket, which is an installation fault. A leak in the media usually means a new filter, so keep a spare of each size on site until the scan is finished.