When the maintenance task only says 'check'

  • Maintenance Service
  • 1 min read

Three ticks close the work order: belt checked, filter checked, pressure checked. Nothing was measured.

The technician did look. The task list gave no instruction beyond the verb, so the result is a tick, and a tick cannot be trended, compared with last quarter or shown to an auditor as evidence of condition.

A task line needs what the word "check" leaves out. The measurement itself: belt tension with a gauge, differential pressure across the pre-filter in pascals, motor current on each phase. Beside it, the acceptable range, taken from the manufacturer's data or the commissioning baseline, and the action when a reading falls outside it.

The form also asks for the as-found value, before any adjustment. A belt found at half its tension and corrected is a different story from a belt found in range, and only the as-found figure tells them apart. It is also what turns a quarterly task into a trend.

Start with the assets your criticality assessment ranks highest and leave the rest for later.

Pull ten closed work orders from last month. How many carry a number?

Related

More on this subject

Who answers for a room's qualified state

"Quality is QA's job" is not how the GMP texts read. The 2013 text of EU GMP Chapter 1 makes the quality objective the responsibility of senior management, with staff in many departments taking part. Chapter 2 lists qualification and maintenance of premises and equipment among the duties the heads of Production and Quality Control generally have.