Condensate flow: a bucket test for coil latent capacity

  • News
  • 1 min read

Remove 170 kg of water an hour at a fresh-air coil and 170 litres go into its drain. You can measure that with a bucket.

Moisture removal is a mass balance. The water leaving the coil equals the dry-air mass flow times the drop in humidity ratio across it. Take 10,000 m³/h of fresh air, about 12,000 kg/h. Bring it from 21 g/kg down to 7 g/kg, roughly a 26 °C and a 9 °C dew point, and the coil has to pull 14 g out of every kilogram: 168 kg/h. Call it 170 litres an hour, close to 3 litres a minute.

So pick a humid afternoon, let the coil run steady for an hour, and put a bucket and a stopwatch on the trap outlet. Log entering and leaving air at the same time. If the design says 170 and the drain gives 110, the coil is short on latent capacity, and you know it before anyone starts arguing about which RH sensor is lying.

A shortfall usually traces to chilled water arriving warmer than design, too little water flow through the coil, or air slipping round the coil frame. Fouled fins come further down the list. Each has its own quick check.

The test depends on the day: on a dry one the result tells you very little.