"We have a process and a site. What should the facility be?" At that point the fresh-air coil can still be any size.
That coil is worth settling first. Take outdoor design air for Ho Chi Minh City. At the hottest-afternoon condition, about 35 °C dry-bulb, it carries roughly 16 g of water per kg of dry air. At the peak dew point condition, about 26 °C dew point at a cooler 29 °C, it carries roughly 21 g/kg. If the coil has to deliver air at about 8 g/kg, the wet afternoon asks it to remove 13 g/kg instead of 8, over 60% more moisture through the same coil.
Size it on the hot afternoon and it comes out with too few rows. The shortfall appears in the first wet season as room humidity drifting above limit. The fix is a deeper coil, which needs a longer casing, which needs a plant room that was drawn around the old one. After tender, each step is a variation.
URS humidity limits and the validation strategy follow the same pattern. Both are cheap to settle while the design is still moving and expensive to retrofit into drawings and protocols.
Our Engineering division works at this stage, and URS, validation strategy and qualification roadmap are written in parallel with the design.
If your project is still at the process-and-site stage, talk to an engineer: contact@humiley.com · +84 28 7777 6668 (Viet Nam office)