The RH you measure in the first month after start-up is partly the building drying out, and that load will not be there in month six.
New concrete slabs, screeds and plaster hold a lot of water when the HVAC starts. They give it up for weeks or months into the room air, and the dehumidification system removes it as if it were part of the design load. It is a temporary latent load that falls away as the building dries.
That sets two traps. The first is commissioning against it: controllers tuned, reheat staged and setpoints nudged to fight moisture the room will not have once it settles. The second is qualifying through it. OQ humidity tests run in the wettest weeks of the building's life either fail for a reason that goes away on its own, or pass on settings that are wrong for steady state.
A dry-out period in the program avoids both. Run the system on its design settings, trend room RH and dew point daily, and start OQ humidity testing once the trend has flattened. The slab, the finishes and the weather outside decide how long that takes, so the program should follow the trend rather than a fixed number of days.
IQ starts from a verified installation. OQ humidity data is worth more when it starts from a building that has stopped giving up its own water.