A 9 °C leaving dew point on a fresh-air coil can be bought two ways, and selection software rarely shows you both.
One way is more coil. Add rows, lower the face velocity, and the leaving air gets close to the water temperature, so the chiller keeps a warmer evaporating temperature. The price is air-side pressure drop. The fan pays it every hour the unit runs, and a GMP supply unit runs nearly all of them.
The other way keeps the coil compact and sends colder water. Now the chiller pays. In an ideal Carnot cycle condensing at 40 °C, COP is Tevap / (Tcond − Tevap), and going from 5 °C to 6 °C evaporating raises it by about 3.3%. Turned around, every kelvin colder costs roughly 3% before real-machine losses are counted.
Which is cheaper depends on things the software does not know: running hours, the tariff, and whether that colder water serves one coil or the whole plant. Dropping an entire chilled-water system by two degrees so one fresh-air unit reaches its dew point is usually the expensive answer. A deeper coil on that unit, or a separate low-temperature circuit, can cost less over ten years.
Our energy modeling at design stage is where that comparison belongs, next to the reheat energy a low dew point brings anyway.
On your last dehumidifying coil, who picked the chilled-water temperature?