Once a HEPA filter is in the ceiling, its proof of class is one test report, tied to it by the serial number on its label.
EN 1822 has filters from H13 upwards tested one by one at the factory, so each should arrive with its own report rather than a batch certificate. A ceiling of 24 terminal filters means 24 reports and 24 serial numbers, and receiving inspection is the last easy moment to match them.
Four things to read on both label and report:
- Class and the standard it was tested to. H14 under EN 1822 means at least 99.995% at the most penetrating particle size.
- Serial number, identical on both. A report that cannot be tied to a serial belongs to some other filter.
- Rated airflow, compared with the airflow schedule for the position the filter is going to.
- The result, with test date and method.
Then record each serial against its ceiling position in the IQ, on the reflected ceiling plan or a filter schedule. It looks like paperwork until a filter fails its installed leak test three years later. With the map, you know which report to pull, which production lot it came from, and whether other filters from that lot sit elsewhere in the building.
A filter that arrives without its individual report waits in quarantine until the report turns up.