Clash detection on an LOD 300 model finds the duct through the beam and misses the hanger rod landing on the cable tray.
The reason is in the definitions. In the BIMForum Level of Development Specification, an LOD 300 element is modelled with its size, shape, location and orientation. LOD 350 adds its interfaces with other building systems, which is where connections, supports, hangers and clearances enter the model.
So a clean clash report at LOD 300 says nothing about the flange that stands proud of the duct, the valve handle with no room to turn or the filter housing with nowhere to pull the filter out. Those surface on site, where each one costs installation time and a variation.
A cleanroom plant room makes this worse than an office. AHUs, clean-utility skids and MCCs need maintenance zones as part of the design, and qualification needs access to test points and sample valves. None of that space exists in a model until someone draws it.
Before anyone relies on a clash report, check which elements actually reached LOD 350. In a plant room the ones that matter most are the AHUs, skids, MCCs and the supports of the main ducts and pipes. A clean result on everything else tells you little.