A production floor mopped after the last shift works like a humidifier the HVAC design never counted.
The physics is one line. Water near room temperature needs about 2,450 kJ per kilogram to evaporate. Spread that over an hour: 2,450 ÷ 3,600 ≈ 0.68 kW for every kilogram per hour of water that leaves the floor, the wash bay or the drying equipment. The room sees it as latent load, and the fresh-air unit has to take it out as condensate.
If 5 kg/h evaporates from freshly cleaned floors and a wash area, that is about 3.4 kW of moisture load. It arrives at the worst moment. Production has stopped, internal heat gains have dropped, the cooling coil unloads because the room is no longer warm, and the dehumidification stage is left alone with a wet room and nothing asking it to run hard.
The symptoms are familiar: RH alarms at night, a humidity excursion in the logs on cleaning days only, condensation on cold surfaces by morning.
The fix is to treat the cleaning shift as its own design case. Estimate the water that evaporates, check the dehumidification stage can remove it with low sensible load, and make sure the control sequence does not throttle dehumidification because the room temperature is satisfied.
Dehumidification staging is one of the primary design decisions we make for tropical plants, alongside coil sizing on peak dew point.