The cheapest air a cleanroom AHU handles is the air it has already cooled and dried.
Recirculated air comes back close to room condition. It needs almost no moisture removed.
Fresh air in Viet Nam's wet season is the opposite. In one worked example, cooling and drying 10,000 m³/h of wet-season outdoor air down to a typical cleanroom supply dew point takes about 186 kW of coil load. Most of that is moisture. The same flow of recirculated air needs a small fraction of it.
So the largest heat recovery device in the building is the return duct. Every m³/h of fresh air you do not need saves more than a wheel or run-around coil will recover from the air you do take in. In GMP rooms a wheel also brings a cross-contamination question you then have to answer.
The avoidable fresh air usually hides in four places. Exhaust set higher than the process needs. Leaky construction, so the AHU makes up for gaps with outdoor air. Room pressures set above what the cascade requires. And 100% fresh air chosen by habit for rooms that do not need it.
Some rooms do need once-through air: potent compounds, solvents. Decide room by room, in the design basis, with the reason written down.
Our energy modeling targets a 30% reduction in HVAC energy, and the first line we examine is fresh air.