Alarm delays justified from door-open transient data

  • News
  • 1 min read

Every pressure alarm delay rests on two numbers.

One is how long a normal door opening takes to recover. The other is how long an excursion can last before it matters.

Every door opening dips the cascade. Without a delay, the EMS alarms on each one; with a delay picked from the last project, nobody can say why it is that value. Both show up badly in an inspection.

The data to set it properly already comes out of OQ, if the test asks for it.

  1. Open each airlock and room door as it is used in operation, with the air system in its normal state, and log the differential at one-second resolution. Note the depth of the dip and the time to recover.
  2. Take the longest normal recovery for that door, add a margin, and that is the floor for the delay.
  3. Set the ceiling from the risk assessment: how long a lost or reversed differential could last before air could carry contamination the wrong way. The delay has to sit below it.
  4. Write both numbers, the recordings and the reasoning into the alarm justification, per room pair.
  5. Add a separate door-held-open alarm, so a long delay never hides a door wedged open.

If the floor comes out higher than the ceiling, the problem is the door, the closer or the airflow, not the alarm setting.

Repeat the recordings after any change to doors, closers or balance.

Our commissioning and qualification work includes FAT, SAT and DQ/IQ/OQ/PQ, and this is one of the OQ recordings worth asking for.

Related

More on this subject

Metadata: what a stored value needs to mean anything

A stored value of 22.4 means nothing without its sensor tag, unit, time stamp, status flag, author and audit trail. The MHRA's 2018 data integrity guidance defines metadata as data that describe the attributes of other data and provide context and meaning. Test that backups, exports and migrations carry them.

InsightRead

Three APS runs across all shifts, and the HVAC has to hold still

Annex 1 initial validation of an aseptic process needs at least 3 consecutive successful simulations covering all working shifts, then periodic runs twice a year per process, line and shift. The cleanroom must hold its qualified state throughout. Agree an HVAC freeze date with QA, and list in advance which jobs are like-for-like and which need an impact assessment.

InsightRead

Two envelopes for a cleanroom HVAC tender

Score the technical envelope of a cleanroom HVAC tender and sign it off before any price is opened. Issue the scoring sheet with the tender: mandatory items pass or fail, the rest weighted, for example 40% technical depth and 20% each for documentation, delivery and service. Score every listed deviation.

InsightRead