Design sensors so they can be calibrated in place

  • Maintenance Service
  • 1 min read

Calibrating one room pressure transmitter should not need a permit to open a cleanroom ceiling.

It often does. The transmitter sits above the ceiling, the tubing runs straight from the wall port to the instrument, and there is nowhere to connect a reference. So the technician opens the ceiling and breaks a tube fitting, and the room loses its pressure reading for the afternoon.

A duct probe fixed three metres up turns calibration into a scaffold job, which gets postponed and then done as a single-point comparison from the BMS screen. A chilled water sensor has no second pocket beside it, so nothing can be compared with it while the system runs.

None of this costs much on the drawing: a test tee with isolating valves on each pressure line, reachable from the floor; probes in a gland or on a flange, so they come out; and a spare thermowell next to each pipe sensor.

Periodic requalification and calibration are part of our maintenance service.

The place to catch it is the instrument installation detail, reviewed by whoever will hold the calibration schedule, before the ceiling goes in.

Related

More on this subject

Three APS runs across all shifts, and the HVAC has to hold still

Annex 1 initial validation of an aseptic process needs at least 3 consecutive successful simulations covering all working shifts, then periodic runs twice a year per process, line and shift. The cleanroom must hold its qualified state throughout. Agree an HVAC freeze date with QA, and list in advance which jobs are like-for-like and which need an impact assessment.

InsightRead

Hold cleanroom pressure on the extract side

A cleanroom is qualified on its supply airflow: air change rate, recovery time and hood velocity. Controlling room pressure by trimming supply moves those numbers with every door opening. Holding supply constant and modulating extract or return keeps the qualified airflow and still holds the pressure cascade.

InsightRead