Yesterday's leak scan failed one terminal HEPA in a Grade C suite. The rooms on either side are in production tomorrow.
With production next door, the order of work is most of the job.
- Open the change control and confirm the replacement is equivalent: same class, dimensions, seal type and rated airflow.
- Stop work in the room, remove or cover product and open equipment, and agree how the neighbouring rooms' pressures will be watched meanwhile.
- Take the old filter out, bag it at the housing and carry it out sealed. Then look at the housing: the knife edge or gasket face, and the gel channel if there is one.
- Fit the new filter and leak-scan it in place, face and perimeter, by the method in ISO 14644-3 (B.7). The filter arrives with a factory test report. The seal between filter and housing was made a few minutes ago and has never been tested.
- Clean the room, then check airflow at the filter, the room pressure differentials, particle counts and recovery before release.
Our maintenance service runs 24/7 corrective and emergency response across Southeast Asia under a maintenance agreement.
EU GMP Annex 1 (2022) names a change of final filters among its examples of changes to consider for requalification, and says the significance of a change should be determined through the change management process. So the extent of the release checks for one filter is argued in the change record, before the work starts.