Changing a terminal HEPA while the suite keeps running

  • Maintenance Service
  • 1 min read

Yesterday's leak scan failed one terminal HEPA in a Grade C suite. The rooms on either side are in production tomorrow.

With production next door, the order of work is most of the job.

  1. Open the change control and confirm the replacement is equivalent: same class, dimensions, seal type and rated airflow.
  2. Stop work in the room, remove or cover product and open equipment, and agree how the neighbouring rooms' pressures will be watched meanwhile.
  3. Take the old filter out, bag it at the housing and carry it out sealed. Then look at the housing: the knife edge or gasket face, and the gel channel if there is one.
  4. Fit the new filter and leak-scan it in place, face and perimeter, by the method in ISO 14644-3 (B.7). The filter arrives with a factory test report. The seal between filter and housing was made a few minutes ago and has never been tested.
  5. Clean the room, then check airflow at the filter, the room pressure differentials, particle counts and recovery before release.

Our maintenance service runs 24/7 corrective and emergency response across Southeast Asia under a maintenance agreement.

EU GMP Annex 1 (2022) names a change of final filters among its examples of changes to consider for requalification, and says the significance of a change should be determined through the change management process. So the extent of the release checks for one filter is argued in the change record, before the work starts.

Industries

Related

More on this subject

Pass boxes: where the grade boundary leaks

A pass box sits across a grade boundary designed for at least 10 Pa. The interlock does not fix a worn door seal, a static box is made safe by the disinfectant contact time rather than by waiting, and a dynamic box needs its supply balanced against both rooms and its HEPA filter leak tested.

InsightRead

A new AHU on a running suite moves the pressure cascade, so its event-driven requalification reaches the differential at every door it serves. Change control sets that scope. Annex 1 (2022) separately caps periodic cleanroom intervals at 6 months for Grade A and B and 12 for C and D.

InsightRead

Three APS runs across all shifts, and the HVAC has to hold still

Annex 1 initial validation of an aseptic process needs at least 3 consecutive successful simulations covering all working shifts, then periodic runs twice a year per process, line and shift. The cleanroom must hold its qualified state throughout. Agree an HVAC freeze date with QA, and list in advance which jobs are like-for-like and which need an impact assessment.

InsightRead