Hold cleanroom pressure on the extract side

  • News
  • 1 min read

If a room's pressure drifts and the BMS answers by trimming supply air, the room is now running on an air change rate nobody qualified.

A cleanroom is qualified on its supply airflow. Air change rate, recovery time and, under a unidirectional flow hood, the air velocity all come from the supply side. Those are the numbers in the OQ report.

Pressure is a different quantity. It comes from the difference between what goes in and what comes out. So the usual control scheme holds supply constant, with a constant-volume box or a flow-measured damper, and sets room pressure by modulating the extract or return damper. A leaky door, a filter loading up, a neighbouring room changing state: the extract damper absorbs them and the supply stays where it was qualified.

Control pressure from the supply side and every disturbance moves the airflow instead. The pressure trend looks fine. The air change rate has quietly changed, and the next requalification finds it.

Two cases need a closer look. Rooms with very little extract, where the damper runs out of authority. And systems where the supply fan itself resets on pressure. Both are design decisions, better made on paper than during commissioning.

In the control narratives we write for cleanroom AHUs, supply flow is a fixed setpoint and pressure lives on the extract.

Related

More on this subject

Three APS runs across all shifts, and the HVAC has to hold still

Annex 1 initial validation of an aseptic process needs at least 3 consecutive successful simulations covering all working shifts, then periodic runs twice a year per process, line and shift. The cleanroom must hold its qualified state throughout. Agree an HVAC freeze date with QA, and list in advance which jobs are like-for-like and which need an impact assessment.

InsightRead

Value engineering after tender: savings that return at OQ

After an over-budget cleanroom HVAC tender, three savings recur: an EN 1886 L2 casing instead of L1, fewer room pressure transmitters, and deleted door drop-seals. Each can reappear as an OQ failure in airflow, alarm testing or pressure differentials, so check every line against its URS requirement and test before accepting it.

InsightRead