65–75%. That is the typical current distortion, THDi, of an EC fan drive without a DC choke.
EC fans save fan power and are easy to control. They also draw current in pulses. Each motor's electronics feed a DC bus through a 6-pulse rectifier, which only takes current near the peaks of the voltage wave. The result is a current rich in 5th, 7th, 11th and 13th harmonics.
With a DC choke, THDi typically drops to 35–42%. Our design target is THDi ≤ 5% at the point of common coupling. IEEE 519-2022 itself limits current distortion as TDD, with limits that depend on the site's short-circuit ratio.
One fan is a small problem. A fan wall of identical units is not. Their harmonic currents are in phase, so they add up instead of cancelling. The effects show up far from the AHU: extra heating in transformers and cables, distorted voltage upsetting other sensitive loads, nuisance tripping, and in some installations resonance with power factor correction capacitors.
In Viet Nam, grid-connection power quality is also a regulatory matter under Circular 05/2025/TT-BCT, so this is a compliance question as well as an engineering one.
What to ask for at design stage: harmonic data per fan from the supplier, DC chokes as standard, and a harmonic study that decides whether an active harmonic filter is needed.