Fresh air or recirculation in a tropical OSD plant: 180 kW against 60 kW

  • Life Sciences
  • 1 min read

On a 10,000 m³/h AHU for a tablet plant in Ho Chi Minh City, full fresh air needs about three times the coil capacity of 20% fresh air.

The sum, with design air at about 88 kJ/kg outdoors, 43 kJ/kg in the return and 34 kJ/kg off the coil: 10,000 m³/h is 3.33 kg/s, and on full fresh air the coil removes about 180 kW of heat and moisture. At 20% fresh air the mixed air reaches the coil at about 52 kJ/kg and the load drops to about 60 kW. Reheat and fan energy come on top of both.

For an OSD plant supplying WHO-GMP markets, that 120 kW is what the WHO guideline on HVAC for non-sterile products leaves to the designer. It allows recirculation where the filtration and a risk assessment support it. Full fresh air removes one cross-contamination route in a multi-product block and pays for it in chiller capacity every hour of the year.

Recirculation keeps most of that energy, and it needs a written case per system: which products share the air, what the return filters are rated to catch, and what happens when one is found damaged.

Dust extraction at the granulator, the blender and the tablet press changes that case. It takes most of the powder out before it reaches the return grille, and makes recirculation much easier to defend.

We fix the destination market in the design basis on day one. For WHO-GMP, this guideline in its current revision is the HVAC reference.

What fresh-air fraction did your last OSD block end up with?

Industries

Related

More on this subject

Zoning and Pressure Cascade

In pharmaceutical facility design, if the HVAC system is the "lungs," then the Zoning and Pressure Cascade strategy is the "immune system." It creates invisible but effective barriers that prevent microbial ingress and strictly control…

InsightRead

In the past, contamination control was often managed in silos: HVAC handled ventilation, Architecture handled walls/ceilings/floors, and QA handled cleaning procedures. But under the updated EU GMP Annex 1, that approach is no longer…

InsightRead