A wrong fan duty found on a live cleanroom site can mean a crane or a cut roof, a delayed OQ and slippage for every trade behind it.
Found in the factory, the same fault means a revised test sheet and a fix before the unit is crated, with no other trade waiting on it. That is the case for a proper Factory Acceptance Test. A useful FAT on a hygienic AHU checks what is hard or impossible to put right once the unit sits in a plant room:
- Dimensions, connections and access doors against the approved GA drawing.
- Casing leakage, tested and recorded against the specified EN 1886 class.
- Fan duty: airflow and pressure at the design point, motor current and rotation.
- Filter frames and seals, so bypass doesn't hide behind a good filter.
- Control wiring and I/O, checked point by point against the schedule.
- Documents: material certificates, weld and passivation records where they apply.
Every AeroSano unit is FAT-tested and witnessed before it ships, and its equipment file is compiled during production, not reconstructed after delivery. IQ then starts from a complete record rather than a hunt for certificates.
If you can send someone to witness the FAT, do, and have them bring the approved specification.